shield
    Lowell House
   Lowell House

March 17, 2009: Sprinkler Project Update

Work will get under starting tomorrow. Below is a detailed day by day outline of the proposed work. Also I have attached a look ahead schedule showing where we expect to be working in each stairwell. I would use the outline and schedule as a guide, as work will progress either a day or so ahead or behind the schedule as proposed.

Contractors will be working thru out the building, but none should need access to your suite. If a situation arises that they need access it will only by escort from Lloyd and or me.

LOWELL HOUSE:

Wednesday 3/18/09:   Sprinkler Subcontractor will be working throughout the building stairwells (all) performing layout of all sprinkler riser penetrations.  The sprinkler subcontractor will also be walking through the basement to layout any penetrations that will be needed in vertical walls.  An Engineering Testing firm will be performing Ground Penetrating Radar inspections throughout the stairwells once layout has been finalized.  Small tools will be delivered into the basement during the day to prepare for work on Friday. 

Thursday 3/19/09:   Sprinkler Subcontractor will be working throughout the building stairwells (all) performing layout of all sprinkler riser penetrations.  The sprinkler subcontractor will also be walking through the basement to layout any penetrations that will be needed in vertical walls.  An Engineering Testing firm will be performing Ground Penetrating Radar inspections throughout the stairwells once layout has been finalized.  Small tools will be delivered into the basement during the day to prepare for work on Friday. 

Friday 3/20/09:   Sprinkler Subcontractor will be working throughout the building stairwells (all) performing layout of all sprinkler riser penetrations.  The sprinkler subcontractor will also be walking through the basement to layout any penetrations that will be needed in vertical walls.  An Engineering Testing firm will be performing Ground Penetrating Radar inspections throughout the stairwells once layout has been finalized.  Asbestos abatement will begin along the west site of the basement at the entrances to the racquetball courts, access to this portion of the building will be limited.  We will be preparing the openings underneath the stairwells of entrances Q, P and O ; we will be cutting into the existing plaster soffits underneath stairwells (NOTE: this will be noisy work). 

Saturday 3/21/09:   Sprinkler Subcontractor will be finalizing the layout of all sprinkler riser penetrations.  The sprinkler subcontractor will also be walking through the basement to layout any penetrations that will be needed in vertical walls.  An Engineering Testing firm will be performing Ground Penetrating Radar inspections throughout the stairwells once layout has been finalized.  Asbestos abatement will continue along the west site of the basement at the entrances to the racquetball courts, access to this portion of the building will be limited.  We will also begin coring the penetrations in the stairwells of Q,P and O (NOTE: Very noisy work).   We will be preparing the openings underneath the stairwells of entrances N,M and L ; we will be cutting into the existing plaster soffits underneath stairwells (NOTE: this will be noisy work). 

Sunday 3/22/09 No Work.

Monday 3/23/09:   The sprinkler subcontractor will continue laying out any penetrations that will be needed in vertical walls throughout the basement.  This will be the final day for the engineering testing firm to complete the Ground Penetrating Radar inspections throughout the stairwells.  Asbestos abatement will continue along the west site of the basement at the entrances to the racquetball courts, access to this portion of the building will be limited.  Installation of new sprinkler piping risers will begin in entries Q,P an O.  We will also begin coring the penetrations in the stairwells of M,N (NOTE: Very noisy work ).  We will be preparing the openings underneath the stairwells of entrances I,F,E and D ; we will be cutting into the existing plaster soffits underneath stairwells (NOTE: this will be noisy work). 

Tuesday 3/24/09:   The sprinkler subcontractor will continue laying out any penetrations that will be needed in vertical walls throughout the basement.  Asbestos abatement will continue along the west site of the basement at the entrances to the racquetball courts, access to this portion of the building will be limited.  Installation of new sprinkler piping risers will continue in entries Q,P,O,N,M and L.  We will also begin coring the penetrations in the stairwells of I,F,E an D (NOTE: Very noisy work) .  We will be preparing the openings underneath the stairwells of entrances C,B and A ; we will be cutting into the existing plaster soffits underneath stairwells (NOTE: this will be noisy work). 

Wednesday 3/25/09:   The sprinkler subcontractor will continue laying out any penetrations that will be needed in vertical walls throughout the basement.  We anticipate that this will be the final day for asbestos abatement in the basement.  We will begin patching the ceiling penetrations underneath the stairwells at entries Q,P and O.  Installation of new sprinkler piping risers will continue in entries N,M,L,I and F.  We will also begin coring the penetrations in the stairwells of E, D, C, B and A, (NOTE: Very noisy work).   We will be preparing the openings underneath the stairwells of entrances C,B and A ; we will be cutting into the existing plaster soffits underneath stairwells (NOTE: this will be noisy work). 

Thursday 3/26/09:   The sprinkler subcontractor will continue laying out any penetrations that will be needed in vertical walls throughout the basement.  We will continue patching the ceiling penetrations underneath the stairwells at entries Q,P,O,N,M and L.  Installation of new sprinkler piping risers will continue in entries I,F,E,D,C,B and A.  We will also begin coring the penetrations in the stairwells of Dining Hall, Entry G and H (NOTE: Very noisy work).  We will be preparing the openings underneath the stairwells of entrance R ; we will be cutting into the existing plaster soffits underneath stairwells (NOTE: this will be noisy work).  

Friday 3/27/09:   The sprinkler subcontractor will continue laying out any penetrations that will be needed in vertical walls throughout the basement.  We will continue patching the ceiling penetrations underneath the stairwells at entries Q,P,O,N,M,L,I & and F.  Installation of new sprinkler piping risers will continue in entries E,D,C,B and A.  We will also begin coring the penetrations in the stairwells of Entry R (NOTE: Very noisy work).  

Saturday 3/28/09: We will continue patching the ceiling penetrations underneath the stairwells at entries N,M,L,I,F,E,D,C,B and A.  Installation of new sprinkler piping risers will continue in entries for the Dining Hall, G, H and R.

Sunday 3/29/09:  No Work

Monday 3/30/09: We will continue patching the ceiling penetrations underneath the stairwells at entries I,F,E,D,C,B,A, Dining Hall, G and H.  Installation of new sprinkler piping risers will continue in entry R.

Thanks

Bob

Bob Sammonds
Lowell House
Building Manager

CONSIGLI CONSTRUCTION CO
Project No. 782 - HARVARD LIFE SAFETY
LOWELL HOUSE & OLD QUINCY SPRING BREAK SCHEDULE
 
ACTIVITY RESP 3/18 3/19 3/20 3/21 3/22 3/23 3/24 3/25 3/26 3/27 3/28 3/29 3/30
    WED THUR FRI SAT SUN MON TUE WED THUR FRI SAT SUN MON
Layout Stairwell Cores JCC                          
GPR Resting BAKER                          
Basement Coring Layout JCC                          
Deliver Tools JCC                          
Deliver risers for J-Q JCC                          
Deliver Basement Pipe O-L JCC                          
Deliver All Remaining Risers JCC                          
Fire Alarm Work / Prep J&M Brown / Alfonso                          
Basement - Abatement Aulson                          
Entry Q CCC,JCC,MASS     Demo/core Demo/core   Pipe Pipe Patch Patch Patch      
Entry P CCC,JCC,MASS     Demo/core Demo/core   Pipe Pipe Patch Patch Patch      
Entry O CCC,JCC,MASS     Demo/core Demo/core   Pipe Pipe Patch Patch Patch      
Entry N CCC,JCC,MASS       Demo/core   Demo/core Pipe Pipe Patch Patch Patch    
Entry M CCC,JCC,MASS       Demo/core   Demo/core Pipe Pipe Patch Patch Patch    
Entry L CCC,JCC,MASS       Demo/core   Demo/core Pipe Pipe Patch Patch Patch    
Entry K CCC,JCC,MASS No Work above Second floor
Entry J CCC,JCC,MASS No Work above Second floor
Entry I CCC,JCC,MASS           Demo/core Demo/core Pipe Pipe Patch Patch   Patch
Entry F CCC,JCC,MASS           Demo/core Demo/core Pipe Pipe Patch Patch   Patch
Entry E CCC,JCC,MASS           Demo/core Demo/core Demo/core Pipe Pipe Patch   Patch
Entry D CCC,JCC,MASS           Demo/core Demo/core Demo/core Pipe Pipe Patch   Patch
Entry C CCC,JCC,MASS             Demo/core Demo/core Pipe Pipe Patch   Patch
Entry B CCC,JCC,MASS             Demo/core Demo/core Pipe Pipe Patch   Patch
Entry A CCC,JCC,MASS             Demo/core Demo/core Pipe Pipe Patch   Patch
Dining Entry CCC,JCC,MASS               Demo/core Demo/core Demo/core Pipe   Patch
Entry G CCC,JCC,MASS               Demo/core Demo/core Pipe Pipe   Patch
Entry H CCC,JCC,MASS               Demo/core Demo/core Pipe Pipe   Patch
Entry R CCC,JCC,MASS                 Demo/core Demo/core Pipe   Pipe
Pipe basement O-L JCC                          

 


Web site design by Alan Wagner